Sewerage Improvement Work Continues in Armagh – Update: Newry Road
07 September 2016 16:13
Work is currently underway on a £3 million programme of work to improve the sewerage network in Armagh. NI Water would like to provide an update on the progress of the work currently taking place on the Newry Road.Due to unforseen circumstances, an extension of 3 weeks is required in order to install the remaining section of the sewer on the Newry Road. This work will be carried out under a lane closure with the use of temporary traffic lights to maintain two way traffic flows.
NI Water is committed to minimising the disruption caused by the complex construction issues associated with this new sewer in a major arterial road into Armagh City, whilst also considering the health and safety of the residents along the route of the sewer.
As residents in the Newry Road area have been subjected to considerable disruption for several weeks over the summer months, the new traffic management arrangements will continue to ensure the safety of residents as well as managing the significantly increased volume of traffic as schools return following the summer holidays.
Night time excavations in roads that are heavily congested with underground utilities including hazardous NIE cables and the main water supply to large areas of Armagh City, was deemed unacceptable as it presents considerable risks to both the construction workers and the residents of Newry Road. Also due to the nature of this work, it is not possible to excavate deep trenches, construct the new sewer and reinstate the road at night to allow the road to be re-opened to traffic during the day.
Therefore working hours will generally be Monday to Friday 7.00am to 7.00pm and Saturday 7.00am to 1.00pm. However on occasion it may be necessary to work outside of these hours.
NI Water will continue to liaise with Transport NI, Armagh City & District Council and all our stakeholders throughout this programme of work to try to minimise disruption as far as possible.
We fully appreciate the disruption caused by these works and NI Water and our contractor, BSG Civil Engineering Ltd, would like to apologise for the inconvenience and thank the public and local businesses for their continued patience and cooperation as we complete these essential works. We assure you that we will do everything we can to complete the work as quickly as practicably possible.
When complete, the scheme will meet Northern Ireland Environment Agency standards, reducing the risk of ‘out of sewer’ flooding and will facilitate future development within Armagh city for the next 30 years by improving and increasing the capacity of the sewerage infrastructure.
Customer queries should be directed to Waterline on 03457 440088.
ENDS
All media enquiries to NI Water press office 028 9035 4710 or email press.office@niwater.com