1
What's under
my site?
Complete a
record request
2
Complete a
Pre-Development
Enquiry (PDE)
Single Unit
3
Impact
assessment
NIW will provide
a completed
report
Agree detail
of solution
identified in
report
Do I want to connect
to both Watermain
and Sewer or
sewer only?
If building
near a Watermain
or Sewer do I need
a diversion?
If there is no existing
watermain or sewer
on my site do i need
an
extension?
4
Apply for a Watermain Diversion
We will contact you
and notify you of any costs
5
Apply for a Sewer diversion
We will contact you and
agree and the design supplied
is suitable. NIW or customer
will
complete this work
6
Apply for a Watermain Extension
We will contact you
and notify you of costs
7
Apply for a Sewer Extension
(Wastewater connection
only). We will contact you
and notify you of costs
8
Applying for &
obtain planning
permission
Agreed solution
to be delivered to allow discharge of planning
conditions
9
Apply for a
water connection
10
Apply for a
Sewer Connection
11
Progress
with Watermain
Diversion
12
Progress
with Watermain
Extension
13
Progress
with Sewer
Diversion
14
Progress
with Watermain
Extension
Complete
water
connections
Complete
Sewer
Connections
Customer action required
NI Water action required